Key Facts
- Permit required
- Yes
- Submission method
- Online
- Typical fee range
- $3,750 – $14,025
- Review time
- Varies by jurisdiction
- Inspections
- 6 inspections required
Limited Data Available
Some information on this page has not been fully verified. We're working to improve data quality. Always verify with Minneapolis directly.
Estimated Total Fees
$3,750 – $14,025
Range based on typical residential solar PV system. Actual fees depend on project valuation and system size.
| Fee Component | Range | Confidence |
|---|---|---|
| ADU Permit Fee[1][2] Building permit fee based on construction valuation (approximately 0.6% of estimated cost). Plan review fee $200-$400. Inspection fees $75-$200 per inspection. Typical 900-1,100 sq ft ADU costs $3,500-$6,500. | $2,500 – $8,500 | ✓ |
| Plan Review Fee[3][4] Plan review fee is typically 50-65% of the permit fee. | $1,250 – $5,525 | ✓ |
| Estimated Total | $3,750 – $14,025 |
Fees shown as ranges. Always verify the exact amount with Minneapolis before submission. Additional fees may apply for expedited review or resubmittals.
Avoid rejections — generate a submission-ready packet
Get a personalized ADU permit packet for Minneapolis, Minnesota — tailored to your project details.
- Required forms: Building Permit Application, and more
- Pre-filled templates: Permit Cover Sheet
- Fee breakdown: $1,250–$8,500 estimated total
- Step-by-step Minneapolis Community Planning and Economic Development portal submission guide
- Inspection prep checklist (6 items)
- Personalized for your specific project details
Free to preview · Pro to download
Required Documents
Minneapolis requires the following documents for this permit application.
Building Permit Application
Completed Minneapolis building permit application with property owner and contractor information
Architectural Plans
Complete architectural drawings signed by licensed Minnesota architect showing floor plans, elevations, sections
Site Plan
Site plan showing lot boundaries, setbacks, existing and proposed structures, parking, utilities, trees, and easements
Energy Code Compliance Documentation
Energy code compliance documentation per Minnesota Energy Code requirements for residential construction
Utility Connection Plans
Plans showing water, sewer, electric, gas connections with utility provider coordination
Owner Certification
Certification of property ownership and authorization for work
Permit Process
Follow these steps to submit your permit application through Minneapolis Community Planning and Economic Development.
- 1
Pre-Application Review
Meet with Minneapolis CPED staff to discuss ADU eligibility under Minneapolis 2040 plan and design requirements
You'll need: Owner Certification
- 2
Submit Building Permit Application
Submit complete permit application with architectural plans, site plan, energy code documentation, and utility plans
You'll need: Building Permit Application, Architectural Plans, Site Plan, Energy Code Compliance Documentation, Utility Connection Plans
- 3
Plan Review and Analysis
CPED plan review team examines plans for compliance with Minneapolis Code Chapter 529 (ADU regulations) and building code
- 4
Submit Revisions
Submit revised plans addressing any code compliance concerns or modifications required by plan reviewer
- 5
Pay Permit Fees
Pay building permit and inspection fees. Permit is issued upon payment
- 6
Construction Inspections
Schedule and pass required inspections: foundation, framing, electrical, plumbing, mechanical, and final
- 7
Certificate of Occupancy
Receive Certificate of Occupancy after final inspection approval
Authority Sources
Data on this page is sourced from official records published by the permitting authority. Always verify requirements directly before submitting.
Minneapolis Community Planning and Economic Development
Last verified: February 15, 2026
1 source referenced
Verified February 15, 2026
Verified February 15, 2026
Verified February 15, 2026
Verified February 15, 2026
Frequently Asked Questions
- Do I need a adu permit in Minneapolis?
- Yes. Minneapolis requires a adu permit for this type of project. Submitting without a permit may result in fines, required removal, or complications when selling your property.
- How long does adu permit approval take in Minneapolis?
- Processing times in Minneapolis vary depending on project complexity and current review volume. The process involves 7 steps. Contact Minneapolis Development Services for current timelines.
- What documents are required for a adu permit in Minneapolis?
- Minneapolis requires 6 documents including Building Permit Application, Architectural Plans, Site Plan, Energy Code Compliance Documentation, and others. See the full list above for details.
- What happens if I build without a adu permit in Minneapolis?
- Building without a permit in Minneapolis can result in stop-work orders, fines, required removal of work, difficulty selling your property, and insurance complications. It is strongly recommended to obtain proper permits before starting work.
- Can PermitMagic help prepare my adu permit submission in Minneapolis?
- Yes. PermitMagic generates a submission-ready packet tailored to Minneapolis's requirements, including a document checklist, workflow steps, and authority references. Start a permit plan to get your personalized packet.
- How much does a adu permit cost in Minneapolis?
- ADU permit fees in Minneapolis typically range from $3,750 to $14,025, depending on project scope. Fees may include building permit, plan review, and technology surcharges. Verify current fees with Minneapolis.
Related Permits
Other permits in Minneapolis
Ready to apply? Build your submission packet.
Answer a few project questions and get a adu permit packet for Minneapolis, Minnesota — with every document, form, and fee organized for submission.
Build My Permit PacketFree to preview · Pro to download