Solar PV Permit Submission Checklist in Fort Worth, Texas

Everything you need to apply for a solar pv permit in Fort Worth, Texas — documents, fees, steps, and a downloadable submission packet.

Key Facts

Permit required
Yes
Submission method
Online
Typical fee range
$263 – $619
Review time
Varies by jurisdiction
Inspections
4 inspections required
VerifiedLast verified: Feb 15, 20262 verified sources

Solar PV Permit Checklist

Fort Worth6 required, 0 optional

Plans & Diagrams(2)

  • Engineering PlansREQUIRED[1][2]

    Electrical and structural engineering plans stamped by licensed professional engineer

  • Site Diagram with SetbacksREQUIRED[5][6]

    Site diagram showing property lines, setbacks, and solar array location

Supporting Documents(4)

  • Product Data SheetsREQUIRED[3][4]

    Complete product data for all electrical components and mounting hardware

  • Structural Review LetterREQUIRED[7][8]

    Licensed structural engineer review of roof loading and attachment adequacy

  • Utility Interconnection AgreementREQUIRED[9][10]

    Signed or pre-approval interconnection agreement from Oncor Electric Delivery

  • Property Owner AuthorizationREQUIRED[11][12]

    Written authorization from current property owner for installation

This checklist is for reference only. Requirements may change — always verify with Fort Worth before submission.

Generate your permit packet

Get a personalized Solar PV permit packet for Fort Worth, Texas — tailored to your project details.

  • Complete list of required forms and documents
  • Pre-filled templates: Permit Cover Sheet
  • Fee breakdown: $88–$375 estimated total
  • Step-by-step Development Services portal submission guide
  • Inspection prep checklist (4 items)
  • Personalized for your specific project details
Build My Permit Packet

Free to preview · Pro to download

Required Documents

Fort Worth requires the following documents for this permit application.

R

Engineering Plans

Electrical and structural engineering plans stamped by licensed professional engineer

R

Product Data Sheets

Complete product data for all electrical components and mounting hardware

R

Site Diagram with Setbacks

Site diagram showing property lines, setbacks, and solar array location

R

Structural Review Letter

Licensed structural engineer review of roof loading and attachment adequacy

R

Utility Interconnection Agreement

Signed or pre-approval interconnection agreement from Oncor Electric Delivery

R

Property Owner Authorization

Written authorization from current property owner for installation

Permit Process

Follow these steps to submit your permit application through Development Services.

  1. 1

    Prepare and Submit Application

    Prepare application with engineering plans and property authorization and submit online or in-person

    You'll need: Engineering Plans, Product Data Sheets, Site Diagram with Setbacks, Property Owner Authorization

  2. 2

    Submit Structural and Utility Documents

    Submit structural review and utility interconnection agreement

    You'll need: Structural Review Letter, Utility Interconnection Agreement

  3. 3

    Building Plan Review

    Fort Worth Development Services performs plan review of structural systems

    You'll need: Engineering Plans, Structural Review Letter

  4. 4

    Electrical Plan Review

    Electrical plan review for NEC compliance and utility coordination

    You'll need: Engineering Plans, Utility Interconnection Agreement

  5. 5

    Issue Permit

    Issuance of combined electrical and building permit

  6. 6

    Inspections and Final Certification

    Rough and final electrical inspections with final certification of compliance

Fees and Timeline

Fee Breakdown

FeeRangeConfidence
Solar PV Permit Fee$175 – $375Verified
Plan Review Fee$88 – $244Verified

Inspections Required

Verify all materials are listed and labeled per UL standards

Verify all materials are listed and labeled per UL standards

Check proper conduit material and support for all electrical

Check proper conduit material and support for all electrical runs

Confirm disconnect switch placement meets NEC 690.13 and 690

Confirm disconnect switch placement meets NEC 690.13 and 690.14

Validate mounting system installation and roof waterproofing

Validate mounting system installation and roof waterproofing

Authority Sources

Data on this page is sourced from official records published by the permitting authority. Always verify requirements directly before submitting.

Development Services

Last verified: February 15, 2026

2 sources referenced

Official page
Fort Worth Solar Permit Information

Verified February 15, 2026

Official page
Solar Permit Requirements and Checklist

Verified February 15, 2026

Official page

Frequently Asked Questions

Do I need a solar pv permit in Fort Worth?
Yes. Fort Worth requires a solar pv permit for this type of project. Submitting without a permit may result in fines, required removal, or complications when selling your property.
How long does solar pv permit approval take in Fort Worth?
Processing times in Fort Worth vary depending on project complexity and current review volume. The process involves 6 steps. Contact Fort Worth Development Services for current timelines.
What documents are required for a solar pv permit in Fort Worth?
Fort Worth requires 6 documents including Engineering Plans, Product Data Sheets, Site Diagram with Setbacks, Structural Review Letter, and others. See the full list above for details.
What happens if I build without a solar pv permit in Fort Worth?
Building without a permit in Fort Worth can result in stop-work orders, fines, required removal of work, difficulty selling your property, and insurance complications. It is strongly recommended to obtain proper permits before starting work.
Can PermitMagic help prepare my solar pv permit submission in Fort Worth?
Yes. PermitMagic generates a submission-ready packet tailored to Fort Worth's requirements, including a document checklist, workflow steps, and authority references. Start a permit plan to get your personalized packet.
How much does a solar pv permit cost in Fort Worth?
Solar PV permit fees in Fort Worth typically range from $263 to $619, depending on project scope. Fees may include building permit, plan review, and technology surcharges. Verify current fees with Fort Worth.

Related Permits

Solar PV permits in nearby cities

Ready to apply? Build your submission packet.

Answer a few project questions and get a solar pv permit packet for Fort Worth, Texas — with every document, form, and fee organized for submission.

Build My Permit Packet