Solar PV Permit Inspection Checklist in Irving, Texas

Everything you need to apply for a solar pv permit in Irving, Texas — documents, fees, steps, and a downloadable submission packet.

Key Facts

Permit required
Yes
Submission method
Online
Typical fee range
$225 – $660
Review time
Varies by jurisdiction
Inspections
4 inspections required
VerifiedLast verified: Feb 15, 20262 verified sources

Inspection Checklist (4 items)

Inspection requirements may vary by project. Always confirm specific inspection criteria with your inspector or local AHJ.

Avoid rejections — generate a submission-ready packet

Get a personalized Solar PV permit packet for Irving, Texas — tailored to your project details.

  • Complete list of required forms and documents
  • Pre-filled templates: Permit Cover Sheet
  • Fee breakdown: $75–$400 estimated total
  • Step-by-step Building Inspections Division portal submission guide
  • Inspection prep checklist (4 items)
  • Personalized for your specific project details
Build My Permit Packet

Free to preview · Pro to download

Required Documents

Irving requires the following documents for this permit application.

R

Solar System Design Plan

Complete design plan prepared by licensed professional with electrical and structural details

R

Calculation and Analysis Documentation

Electrical calculations, load analysis, and grounding study for the system

R

Component Specifications

Technical data sheets for inverter, combiner boxes, modules, and other equipment

R

Structural Engineering Report

Licensed structural engineer report certifying roof and mounting system adequacy

R

Property Owner Consent Document

Written consent from property owner authorizing solar system installation

R

Utility Coordination Letter

Letter of coordination with utility company regarding interconnection plans

Permit Process

Follow these steps to submit your permit application through Building Inspections Division.

  1. 1

    Prepare Online Application

    Prepare and submit solar permit application through City of Irving online portal

    You'll need: Solar System Design Plan, Component Specifications, Property Owner Consent Document

  2. 2

    Upload Supporting Analysis

    Upload structural report, calculations, and utility coordination documentation

    You'll need: Calculation and Analysis Documentation, Structural Engineering Report, Utility Coordination Letter

  3. 3

    Building Plan Examination

    Building Services examines structural design and roof mounting system

    You'll need: Solar System Design Plan, Structural Engineering Report

  4. 4

    Electrical Design Review

    Electrical inspector reviews design for NEC compliance and utility interface

    You'll need: Solar System Design Plan, Calculation and Analysis Documentation

  5. 5

    Issue Construction Permit

    Issuance of electrical and building construction permit

  6. 6

    Conduct Inspections

    Schedule and perform rough electrical and final electrical inspections

Fees and Timeline

Fee Breakdown

FeeRangeConfidence
Solar PV Permit Fee$150 – $400Verified
Plan Review Fee$75 – $260Verified

Inspections Required

Verify all electrical connections per approved design specif

Verify all electrical connections per approved design specifications

Check DC and AC disconnect switches for proper installation

Check DC and AC disconnect switches for proper installation and labeling

Confirm roof mounting hardware installation and weatherproof

Confirm roof mounting hardware installation and weatherproofing

Validate grounding system conductors and bonding connections

Validate grounding system conductors and bonding connections

Authority Sources

Data on this page is sourced from official records published by the permitting authority. Always verify requirements directly before submitting.

Building Inspections Division

Last verified: February 15, 2026

2 sources referenced

Portal guide
Official page
Irving Solar Installation Standards

Verified February 15, 2026

Official page

Frequently Asked Questions

Do I need a solar pv permit in Irving?
Yes. Irving requires a solar pv permit for this type of project. Submitting without a permit may result in fines, required removal, or complications when selling your property.
How long does solar pv permit approval take in Irving?
Processing times in Irving vary depending on project complexity and current review volume. The process involves 6 steps. Contact Irving Development Services for current timelines.
What documents are required for a solar pv permit in Irving?
Irving requires 6 documents including Solar System Design Plan, Calculation and Analysis Documentation, Component Specifications, Structural Engineering Report, and others. See the full list above for details.
What happens if I build without a solar pv permit in Irving?
Building without a permit in Irving can result in stop-work orders, fines, required removal of work, difficulty selling your property, and insurance complications. It is strongly recommended to obtain proper permits before starting work.
Can PermitMagic help prepare my solar pv permit submission in Irving?
Yes. PermitMagic generates a submission-ready packet tailored to Irving's requirements, including a document checklist, workflow steps, and authority references. Start a permit plan to get your personalized packet.
How much does a solar pv permit cost in Irving?
Solar PV permit fees in Irving typically range from $225 to $660, depending on project scope. Fees may include building permit, plan review, and technology surcharges. Verify current fees with Irving.

Related Permits