Key Facts
- Permit required
- Yes
- Submission method
- Online
- Typical fee range
- $225 – $578
- Review time
- Varies by jurisdiction
- Inspections
- 4 inspections required
Inspection Checklist (4 items)
Inspection requirements may vary by project. Always confirm specific inspection criteria with your inspector or local AHJ.
Avoid rejections — generate a submission-ready packet
Get a personalized Solar PV permit packet for Aurora, Colorado — tailored to your project details.
- Required forms: Building Permit Application, and more
- Pre-filled templates: Permit Cover Sheet
- Fee breakdown: $75–$350 estimated total
- Step-by-step City of Aurora Planning and Development Services portal submission guide
- Inspection prep checklist (4 items)
- Personalized for your specific project details
Free to preview · Pro to download
Required Documents
Aurora requires the following documents for this permit application.
Building Permit Application
Aurora building permit application for solar PV system installation
Site Plan and Roof Layout
Scaled site plan showing solar array placement and property setbacks
Electrical Single-Line Diagram
Complete electrical diagram with inverter, disconnects, and grounding systems
Solar Equipment Specifications
Solar module and inverter specifications with UL certifications
Structural Evaluation Letter
Licensed professional engineer letter confirming structural capacity
System Design Documentation
Detailed system design including capacity, performance, and safety features
Interconnection Agreement
Utility company interconnection agreement or notification
Permit Process
Follow these steps to submit your permit application through City of Aurora Planning and Development Services.
- 1
Application Submission
Submit complete building permit application with site plan and structural verification
You'll need: Building Permit Application, Site Plan and Roof Layout, Structural Evaluation Letter
- 2
Plan Review
Comprehensive review of electrical and structural plans
You'll need: Electrical Single-Line Diagram, Solar Equipment Specifications, System Design Documentation
- 3
Utility Coordination
Submit interconnection documentation to utility company
You'll need: Interconnection Agreement
- 4
Permit Issuance
Issue building permit upon plan review approval
- 5
Construction and Inspection
Install system and request inspections at key milestones
- 6
Final Inspection and Certificate
Conduct final inspection and issue certificate of occupancy
Fees and Timeline
Fee Breakdown
| Fee | Range | Confidence |
|---|---|---|
| Solar PV Permit Fee | $150 – $350 | Verified |
| Plan Review Fee | $75 – $228 | Verified |
Inspections Required
Verify mounting system installation and fastening
Verify mounting system installation and fastening
Test electrical connections and grounding systems
Test electrical connections and grounding systems
Inspect structural attachments and roof integrity
Inspect structural attachments and roof integrity
Confirm disconnect switches and safety labeling
Confirm disconnect switches and safety labeling
Authority Sources
Data on this page is sourced from official records published by the permitting authority. Always verify requirements directly before submitting.
City of Aurora Planning and Development Services
Last verified: February 15, 2026
2 sources referenced
Verified February 15, 2026
Verified February 15, 2026
Verified February 15, 2026
Frequently Asked Questions
- Do I need a solar pv permit in Aurora?
- Yes. Aurora requires a solar pv permit for this type of project. Submitting without a permit may result in fines, required removal, or complications when selling your property.
- How long does solar pv permit approval take in Aurora?
- Processing times in Aurora vary depending on project complexity and current review volume. The process involves 6 steps. Contact Aurora Development Services for current timelines.
- What documents are required for a solar pv permit in Aurora?
- Aurora requires 7 documents including Building Permit Application, Site Plan and Roof Layout, Electrical Single-Line Diagram, Solar Equipment Specifications, and others. See the full list above for details.
- What happens if I build without a solar pv permit in Aurora?
- Building without a permit in Aurora can result in stop-work orders, fines, required removal of work, difficulty selling your property, and insurance complications. It is strongly recommended to obtain proper permits before starting work.
- Can PermitMagic help prepare my solar pv permit submission in Aurora?
- Yes. PermitMagic generates a submission-ready packet tailored to Aurora's requirements, including a document checklist, workflow steps, and authority references. Start a permit plan to get your personalized packet.
- How much does a solar pv permit cost in Aurora?
- Solar PV permit fees in Aurora typically range from $225 to $578, depending on project scope. Fees may include building permit, plan review, and technology surcharges. Verify current fees with Aurora.
Related Permits
Other permits in Aurora
Solar PV permits in nearby cities
Ready to apply? Build your submission packet.
Answer a few project questions and get a solar pv permit packet for Aurora, Colorado — with every document, form, and fee organized for submission.
Build My Permit PacketFree to preview · Pro to download